Skip to content

Use mind maps

A mind map shows a Project's Runs as a tree, with each Run branching from its baseline, so you can follow a development story and see what each change gained. Each node can show a result and its delta to its parent, and has its own whiteboard, the Node Report, for notes, tables and postpro.

Before you start

  • Mind maps are in beta: the sidebar shows Mind Maps (Beta).
  • Select a Programme and a Project in the header. New Mind Map is disabled until you do ("Select a project to make mind map.").
  • The values shown on the nodes come from a Results table view. See create a table view.

Create a mind map

  1. In the sidebar, under Visualisation & Data, click Mind Maps (Beta).
  2. Click New Mind Map. Create Mind Map opens.
  3. Fill in the form:

    Field Required Notes
    Name Yes Up to 200 characters. Must be unique in the Project (* This name is already in use. *)
    Description No Up to 200 characters
    Results View Yes The table view whose columns you can show on the nodes
  4. Click Create Mind Map, then open it from the list.

  5. A new mind map is empty. Click Update All, then Update All again to confirm. Bramble adds every Run in the Project, including their baselines, linked by baseline.

Run Update All again whenever the Project has new Runs. It adds the Runs that aren't on the map yet and keeps the existing nodes.

To delete a mind map, click its delete icon in the list, then Confirm. Only its creator can delete it.

Add nodes

Each node is a Run. Its parent is the Run's baseline. A baseline in another Project appears as an extra node.

To add Runs from other Programmes or Projects:

  1. Click Add Node.
  2. Under Choose Attitudes, choose the Programme and Project, then tick the Runs.
  3. Click Add Node(s).

The Programme is locked once you've picked Runs. Deselect them to change it. A Run that's already on the map gives "Node Already Exists".

Show results on the nodes

Use the toolbar above the map:

Control Does
Attitude: The Attitude whose results the nodes show, from those the Runs share
Variable: A column of the mind map's Results View. The eye icon shows or hides the values
Deltas: Absolute, Percentage or None: the change from each node's parent
Centre Map Centres the map
Show All Shows hidden nodes again

Drag to pan, scroll to zoom and drag nodes to arrange them. The map saves automatically; Saved at: shows when.

To change a node's parent, drag it onto another node. When the target highlights, release. The deltas then compare against the new parent. The link doesn't change the Run's baseline.

Click a node for its menu:

Option Does
Hide Node Hides the node. Show All brings it back
Show/Hide Parents Shows or hides the branch above the node
Show/Hide Children Shows or hides the branch below the node
Disconnect Node Removes the link to its parent
Delete Node Removes the node from the mind map
Show Geometry Opens the Run's geometry plots, if they've been generated
Reporting Opens the node's Node Report

Write a Node Report

Each node has one Node Report per mind map: a whiteboard for the story behind that Run.

  1. Click the node, then Reporting. The Node Report opens full screen, titled with the Run name.
  2. Add content with the tools along the top:
    • Text Box tool, Rectangle tool, Ellipse tool, Line tool, Arrow tool and Ruler tool
    • Add Results Table: see add a table
    • Open Postpro Window: see add postpro
    • Select tool, Pan tool, Eraser tool, Undo tool and Redo tool
  3. Select an item to change its font, border, fill, line style, layer order or alignment in the side menu.
  4. Open the menu and click Save, or Save & Exit.

The grid menu has No Grid, Add Gridlines and Add Dot Grid. The menu also has Exit Without Saving and Export as JSON.

Warning

Node Reports don't save automatically. If you close one with unsaved changes, Close Report asks you to choose Exit Without Saving or Save & Exit.

Add a table

  1. Click Add Results Table.
  2. In the side menu, choose the Table View: and the Attitudes (Select Node Attitude(s), or Select All).
  3. Click Create Table.

You can add more than one table. After the first, the tool's tooltip reads "Results table already exists", but it still works.

Add postpro

  1. Click Open Postpro Window. In the side menu, choose from Baseline Attitudes: and Run Attitudes:, then click Show.
  2. In the postpro viewer, pick an image and click Add to Whiteboard. You can also drag a thumbnail onto the whiteboard.

Postpro with an overlay can't be added, and you can only add one GIF at a time.

For a movie, choose Add as frame for a still, or Add as GIF. With Add as GIF, set the GIF Options:

Option Choices
Frame Rate: Slowest (1 fps), Slow (5 fps), Default (10 fps), Fast (30 fps), Fastest (50 fps)
Reflect: Plays the movie forwards then backwards, instead of jumping back to the start
Frame Selection: Range: set First Frame: and Last Frame: with the slider. Specific Frames: click Add Current Frame to GIF for each frame, and drag the Selected Frames list to reorder

Related: Create a table view · Compare results in the postpro viewer · Create a report · Results and post-processing